Yunnan Honghe Prefecture 2.2GW Wind and Solar Index Optimization Results Public Announcement: China Three Gorges, Huaneng, Huadian, Yunnan Energy Investment and Others Listed

(Source: Fengmang Energy)

Fengmang Energy has learned that on March 20, the People’s Government of Honghe Hani and Yi Autonomous Prefecture in Yunnan Province announced the public notice of the selected construction owners for 34 new energy projects included in the third batch of Yunnan Province’s 2025 New Energy Construction List.

The announcement shows that the 34 new energy projects listed in the 2025 third batch of Yunnan Province’s new energy construction list have a total capacity of 2,224 MW, including 12 photovoltaic projects with a total capacity of 660 MW and 22 wind power projects with a total capacity of 1,564 MW.

In terms of project owners, Hongqiao New Materials has the largest scale of new energy indicators at 849 MW. Huaihe Energy Holding Group follows with over 400 MW. Next are Huaneng and Sichuan Shengxinyuan Construction Engineering Consortium, Jinko and Jiangsu Meike Solar Consortium, Huaneng, and Yunnan Energy Investment Group, each with indicators exceeding 100 MW.

Details are as follows:

At the request of the Honghe Energy Bureau, Honghe Construction Engineering Bidding Co., Ltd. completed the evaluation of the selection of construction owners for the 34 new energy projects included in the third batch of Yunnan Province’s 2025 New Energy Construction List on March 19-20, 2026, at the conference room on the 2nd floor of Honghe Construction Engineering Bidding Co., Ltd. (No. 8, Hongjian Jiayuan Business Network, Huguo Road, Mengzi City, Honghe Prefecture). After evaluation by the expert panel, the entrusted party confirmed the results, which are now publicly announced as follows:

(1) Project Name: Qilu Bai Photovoltaic Power Generation Project Construction Owner Selection

  1. Project Capacity: Proposed installed capacity of 50,000 kW.

  2. Planned Investment: 200 million yuan.

  3. Construction Period: According to the construction period stipulated in Yunnan Development and Reform Energy [2023] No. 264 and Yunnan Energy New Energy [2025] No. 287 documents.

  4. Location: Qilu Bai Township, Mengzi City.

  5. Project Category: Centralized Photovoltaic.

Selected Enterprises: Jinko Power Technology Co., Ltd., Yunnan Jiatailai New Materials Co., Ltd. (Joint Venture)

(2) Project Name: Chake Photovoltaic Power Generation Project Construction Owner Selection

  1. Project Capacity: Proposed installed capacity of 70,000 kW.

  2. Planned Investment: 280 million yuan.

  3. Construction Period: As per the construction period stipulated in Yunnan Development and Reform Energy [2023] No. 264 and Yunnan Energy New Energy [2025] No. 287.

  4. Location: Chake Town and Panjiang Township, Jianshui County.

  5. Project Category: Centralized Photovoltaic.

Selected Enterprise: Honghe Hongfa New Infrastructure Investment and Operation Co., Ltd.

(3) Project Name: Qujiang Photovoltaic Power Generation Project Construction Owner Selection

  1. Project Capacity: Proposed installed capacity of 25,000 kW.

  2. Planned Investment: 100 million yuan.

  3. Construction Period: As per the construction period stipulated in Yunnan Development and Reform Energy [2023] No. 264 and Yunnan Energy New Energy [2025] No. 287.

  4. Location: Qujiang Town, Jianshui County.

  5. Project Category: Centralized Photovoltaic.

Selected Enterprises: Jinko Power Technology Co., Ltd., Yunnan Jiatailai New Materials Co., Ltd. (Joint Venture)

(4) Project Name: Wanjia Zhuang Photovoltaic Power Generation Project Construction Owner Selection

  1. Project Capacity: Proposed installed capacity of 50,000 kW.

  2. Planned Investment: 200 million yuan.

  3. Construction Period: As per the construction period stipulated in Yunnan Development and Reform Energy [2023] No. 264 and Yunnan Energy New Energy [2025] No. 287.

  4. Location: Mian Dian Town and Puxiong Township, Jianshui County.

  5. Project Category: Centralized Photovoltaic.

Selected Enterprise: Yunnan Green Energy Industry Group Co., Ltd.

(5) Project Name: Qike Tree Photovoltaic Power Generation Project Construction Owner Selection

  1. Project Capacity: Proposed installed capacity of 55,000 kW.

  2. Planned Investment: 220 million yuan.

  3. Construction Period: As per the construction period stipulated in Yunnan Development and Reform Energy [2023] No. 264 and Yunnan Energy New Energy [2025] No. 287.

  4. Location: Mian Dian Town, Jianshui County.

  5. Project Category: Centralized Photovoltaic.

Selected Enterprise: Yunnan Green Energy Industry Group Co., Ltd.

(6) Project Name: Nanzhuang Photovoltaic Power Generation Project (Phase III) Construction Owner Selection

  1. Project Capacity: Proposed installed capacity of 40,000 kW.

  2. Planned Investment: 160 million yuan.

  3. Construction Period: As per the construction period stipulated in Yunnan Development and Reform Energy [2023] No. 264 and Yunnan Energy New Energy [2025] No. 287.

  4. Location: Nanzhuang Town, Jianshui County.

  5. Project Category: Centralized Photovoltaic.

Selected Enterprise: Guotou New Energy (Honghe) Co., Ltd.

(7) Project Name: Hongtian Photovoltaic Power Generation Project (Phase II) Construction Owner Selection

  1. Project Capacity: Proposed installed capacity of 60,000 kW.

  2. Planned Investment: 240 million yuan.

  3. Construction Period: As per the construction period stipulated in Yunnan Development and Reform Energy [2023] No. 264 and Yunnan Energy New Energy [2025] No. 287.

  4. Location: Mian Dian Town and Chake Town, Jianshui County.

  5. Project Category: Centralized Photovoltaic.

Selected Enterprise: Jinko Power Technology Co., Ltd., Yunnan Jiatailai New Materials Co., Ltd. (Joint Venture)

(8) Project Name: Baishi Yan Wind Farm (Phase I) Construction Owner Selection

  1. Project Capacity: Proposed installed capacity of 70,000 kW.

  2. Planned Investment: 315 million yuan.

  3. Construction Period: As stipulated in Yunnan Energy New Energy [2025] No. 287.

  4. Location: Jixiang Town, Gucheng Street, Laochang Town, Gejiu City.

  5. Project Category: Centralized Wind Power.

Selected Enterprise: Yunnan Hongqiao New Energy Co., Ltd.

(9) Project Name: Baishi Yan Wind Farm (Phase II) Construction Owner Selection

  1. Project Capacity: Proposed installed capacity of 55,000 kW.

  2. Planned Investment: 247.5 million yuan.

  3. Construction Period: As stipulated in Yunnan Energy New Energy [2025] No. 287.

  4. Location: Jashaxiang and Jixiang Town, Gejiu City.

  5. Project Category: Centralized Wind Power.

Selected Enterprise: Yunnan Hongqiao New Energy Co., Ltd.

(10) Project Name: Lianhua Mountain Wind Farm (Phase III) Construction Owner Selection

  1. Project Capacity: Proposed installed capacity of 75,000 kW.

  2. Planned Investment: 337.5 million yuan.

  3. Construction Period: As stipulated in Yunnan Energy New Energy [2025] No. 287.

  4. Location: Kafang Town, Gejiu City.

  5. Project Category: Centralized Wind Power.

Selected Enterprise: Huaneng (Yunnan) New Energy Power Generation Co., Ltd.

(11) Project Name: Mazha Siao Wind Farm Construction Owner Selection

  1. Project Capacity: Proposed installed capacity of 100,000 kW.

  2. Planned Investment: 450 million yuan.

  3. Construction Period: As stipulated in Yunnan Energy New Energy [2025] No. 287.

  4. Location: Zhongheying Town and Beige Township, Kaiyuan City.

  5. Project Category: Centralized Wind Power.

Selected Enterprise: Yunnan Hongqiao New Energy Co., Ltd.

(12) Project Name: Lengquan Wind Farm (Phase I) Construction Owner Selection

  1. Project Capacity: Proposed installed capacity of 77,000 kW.

  2. Planned Investment: 346.5 million yuan.

  3. Construction Period: As stipulated in Yunnan Energy New Energy [2025] No. 287.

  4. Location: Minghui Town, Mengzi City.

  5. Project Category: Centralized Wind Power.

Selected Enterprise: Yunnan Hongqiao New Energy Co., Ltd.

(13) Project Name: Lengquan Wind Farm (Phase II) Construction Owner Selection

  1. Project Capacity: Proposed installed capacity of 168,000 kW.

  2. Planned Investment: 756 million yuan.

  3. Construction Period: As stipulated in Yunnan Energy New Energy [2025] No. 287.

  4. Location: Northwest Le Township and Minghui Town, Mengzi City.

  5. Project Category: Centralized Wind Power.

Selected Enterprise: Yunnan Hongqiao New Energy Co., Ltd.

(14) Project Name: Duogu Wind Farm (Phase II) Construction Owner Selection

  1. Project Capacity: Proposed installed capacity of 50,000 kW.

  2. Planned Investment: 225 million yuan.

  3. Construction Period: As stipulated in Yunnan Energy New Energy [2025] No. 287.

  4. Location: Northwest Le Township, Mengzi City.

  5. Project Category: Centralized Wind Power.

Selected Enterprise: Huaneng (Yunnan) New Energy Power Generation Co., Ltd.

(15) Project Name: Ma Yi Mountain Wind Farm Construction Owner Selection

  1. Project Capacity: Proposed installed capacity of 100,000 kW.

  2. Planned Investment: 450 million yuan.

  3. Construction Period: As stipulated in Yunnan Energy New Energy [2025] No. 287.

  4. Location: Limin Township and Qujiang Town, Jianshui County.

  5. Project Category: Centralized Wind Power.

Selected Enterprise: Yunnan Hongqiao New Energy Co., Ltd.

(16) Project Name: Nanzhuang Wind Farm Construction Owner Selection

  1. Project Capacity: Proposed installed capacity of 18,750 kW.

  2. Planned Investment: 84.375 million yuan.

  3. Construction Period: As stipulated in Yunnan Energy New Energy [2025] No. 287.

  4. Location: Nanzhuang Town and Mian Dian Town, Jianshui County.

  5. Project Category: Centralized Wind Power.

Selected Enterprise: Guotou New Energy (Honghe) Co., Ltd.

(17) Project Name: Feilong Village Wind Farm Construction Owner Selection

  1. Project Capacity: Proposed installed capacity of 76,000 kW.

  2. Planned Investment: 342 million yuan.

  3. Construction Period: As stipulated in Yunnan Energy New Energy [2025] No. 287.

  4. Location: Baoxiu Town, Shiping County.

  5. Project Category: Centralized Wind Power.

Selected Enterprise: Yunnan Hongqiao New Energy Co., Ltd.

(18) Project Name: Yanwashan Wind Farm Construction Owner Selection

  1. Project Capacity: Proposed installed capacity of 66,000 kW.

  2. Planned Investment: 297 million yuan.

  3. Construction Period: As stipulated in Yunnan Energy New Energy [2025] No. 287.

  4. Location: Yilong Town, Shiping County.

  5. Project Category: Centralized Wind Power.

Selected Enterprise: Yunnan Hongqiao New Energy Co., Ltd.

(19) Project Name: Milexi Wind Farm (Phase III) Construction Owner Selection

  1. Project Capacity: Proposed installed capacity of 87,500 kW.

  2. Planned Investment: 393.75 million yuan.

  3. Construction Period: As stipulated in Yunnan Energy New Energy [2025] No. 287.

  4. Location: Xier Town, Mile City.

  5. Project Category: Centralized Wind Power.

Selected Enterprise: China Three Gorges Group Yunnan Energy Investment Co., Ltd.

(20) Project Name: Taiping Wind Farm Construction Owner Selection

  1. Project Capacity: Proposed installed capacity of 75,000 kW.

  2. Planned Investment: 337.5 million yuan.

  3. Construction Period: As stipulated in Yunnan Energy New Energy [2025] No. 287.

  4. Location: Taiping Street, Mile City.

  5. Project Category: Centralized Wind Power.

Selected Enterprises: Datang Yunnan Power Generation Co., Ltd., Mile Yuxing New Materials Co., Ltd. (Joint Venture)

(21) Project Name: Qige Wind Farm Construction Owner Selection

  1. Project Capacity: Proposed installed capacity of 80,000 kW.

  2. Planned Investment: 360 million yuan.

  3. Construction Period: As stipulated in Yunnan Energy New Energy [2025] No. 287.

  4. Location: Pengpu Town, Mile City.

  5. Project Category: Centralized Wind Power.

Selected Enterprise: Yunnan Hongqiao New Energy Co., Ltd.

(22) Project Name: Jibai Wind Farm Construction Owner Selection

  1. Project Capacity: Proposed installed capacity of 57,000 kW.

  2. Planned Investment: 256.5 million yuan.

  3. Construction Period: As stipulated in Yunnan Energy New Energy [2025] No. 287.

  4. Location: Xunjian Si Town and Lebai Road Subdistrict, Mile City.

  5. Project Category: Centralized Wind Power.

Selected Enterprise: Yunnan Hongqiao New Energy Co., Ltd.

(23) Project Name: Yezhu Photovoltaic Power Generation Project Construction Owner Selection

  1. Project Capacity: Proposed installed capacity of 25,000 kW.

  2. Planned Investment: 100 million yuan.

  3. Construction Period: As stipulated in Yunnan Development and Reform Energy [2023] No. 264 and Yunnan Energy New Energy [2025] No. 287.

  4. Location: Qinglong Town, Jianshui County.

  5. Project Category: Centralized Photovoltaic.

Selected Enterprises: Huaneng Hainan Power Generation Co., Ltd., Huaneng Fuxin Wind Power Co., Ltd., Sichuan Shengxinyuan Construction Engineering Co., Ltd. (Joint Venture)

(24) Project Name: Caohai Zi Photovoltaic Power Generation Project Construction Owner Selection

  1. Project Capacity: Proposed installed capacity of 90,000 kW.

  2. Planned Investment: 360 million yuan.

  3. Construction Period: As stipulated in Yunnan Development and Reform Energy [2023] No. 264 and Yunnan Energy New Energy [2025] No. 287.

  4. Location: Lin’an Town and Qinglong Town, Jianshui County.

  5. Project Category: Centralized Photovoltaic.

Selected Enterprises: Huaneng Hainan Power Generation Co., Ltd., Huaneng Fuxin Wind Power Co., Ltd., Sichuan Shengxinyuan Construction Engineering Co., Ltd. (Joint Venture)

(25) Project Name: Kezu Photovoltaic Power Generation Project Construction Owner Selection

  1. Project Capacity: Proposed installed capacity of 70,000 kW.

  2. Planned Investment: 280 million yuan.

  3. Construction Period: As stipulated in Yunnan Development and Reform Energy [2023] No. 264 and Yunnan Energy New Energy [2025] No. 287.

  4. Location: Xunjian Si Town, Mile City.

  5. Project Category: Centralized Photovoltaic.

Selected Enterprises: Huaneng Hainan Power Generation Co., Ltd., Huaneng Fuxin Wind Power Co., Ltd., Sichuan Shengxinyuan Construction Engineering Co., Ltd. (Joint Venture)

(26) Project Name: Sheshan Photovoltaic Power Generation Project Construction Owner Selection

  1. Project Capacity: Proposed installed capacity of 65,000 kW.

  2. Planned Investment: 260 million yuan.

  3. Construction Period: As stipulated in Yunnan Development and Reform Energy [2023] No. 264 and Yunnan Energy New Energy [2025] No. 287.

  4. Location: Xunjian Si Town, Mile City.

  5. Project Category: Centralized Photovoltaic.

Selected Enterprises: Huaneng Hainan Power Generation Co., Ltd., Huaneng Fuxin Wind Power Co., Ltd., Sichuan Shengxinyuan Construction Engineering Co., Ltd. (Joint Venture)

(27) Project Name: Potou Photovoltaic Power Generation Project Construction Owner Selection

  1. Project Capacity: Proposed installed capacity of 60,000 kW.

  2. Planned Investment: 240 million yuan.

  3. Construction Period: As stipulated in Yunnan Development and Reform Energy [2023] No. 264 and Yunnan Energy New Energy [2025] No. 287.

  4. Location: Nansha Town, Yuan Yang County.

  5. Project Category: Centralized Photovoltaic.

Selected Enterprises: Huaneng Hainan Power Generation Co., Ltd., Huaneng Fuxin Wind Power Co., Ltd., Sichuan Shengxinyuan Construction Engineering Co., Ltd. (Joint Venture)

(28) Project Name: Laozu Ji Wind Farm Construction Owner Selection

  1. Project Capacity: Proposed installed capacity of 60,000 kW.

  2. Planned Investment: 270 million yuan.

  3. Construction Period: As stipulated in Yunnan Energy New Energy [2025] No. 287.

  4. Location: Lengquan Town, Mengzi City.

  5. Project Category: Centralized Wind Power.

Selected Enterprise: Huaihe Energy (Group) Co., Ltd.

(29) Project Name: Taqikou Wind Farm Construction Owner Selection

  1. Project Capacity: Proposed installed capacity of 100,000 kW.

  2. Planned Investment: 450 million yuan.

  3. Construction Period: As stipulated in Yunnan Energy New Energy [2025] No. 287.

  4. Location: Xibei Le Township and Mingjiao Town, Mengzi City.

  5. Project Category: Centralized Wind Power.

Selected Enterprise: Huaihe Energy (Group) Co., Ltd.

(30) Project Name: Lujinshan Wind Farm Construction Owner Selection

  1. Project Capacity: Proposed installed capacity of 55,000 kW.

  2. Planned Investment: 247.5 million yuan.

  3. Construction Period: As stipulated in Yunnan Energy New Energy [2025] No. 287.

  4. Location: Wencui Street and Lengquan Town, Mengzi City.

  5. Project Category: Centralized Wind Power.

Selected Enterprise: Huaihe Energy (Group) Co., Ltd.

(31) Project Name: Daniu Wind Farm (Phase III) Construction Owner Selection

  1. Project Capacity: Proposed installed capacity of 56,250 kW.

  2. Planned Investment: 253.125 million yuan.

  3. Construction Period: As stipulated in Yunnan Energy New Energy [2025] No. 287.

  4. Location: Niujie Town, Shiping County.

  5. Project Category: Centralized Wind Power.

Selected Enterprise: Huaihe Energy (Group) Co., Ltd.

(32) Project Name: Liangchong Wind Farm Construction Owner Selection

  1. Project Capacity: Proposed installed capacity of 45,000 kW.

  2. Planned Investment: 202.5 million yuan.

  3. Construction Period: As stipulated in Yunnan Energy New Energy [2025] No. 287.

  4. Location: Longwu Town, Shiping County.

  5. Project Category: Centralized Wind Power.

Selected Enterprise: Huaihe Energy (Group) Co., Ltd.

(33) Project Name: Linma Wind Farm Construction Owner Selection

  1. Project Capacity: Proposed installed capacity of 37,500 kW.

  2. Planned Investment: 168.75 million yuan.

  3. Construction Period: As stipulated in Yunnan Energy New Energy [2025] No. 287.

  4. Location: Xitown, Mile City.

  5. Project Category: Centralized Wind Power.

Selected Enterprise: Huaihe Energy (Group) Co., Ltd.

(34) Project Name: Lushuitang Wind Farm Construction Owner Selection

  1. Project Capacity: Proposed installed capacity of 55,000 kW.

  2. Planned Investment: 247.5 million yuan.

  3. Construction Period: As stipulated in Yunnan Energy New Energy [2025] No. 287.

  4. Location: Pengpu Town, Mile City.

  5. Project Category: Centralized Wind Power.

Selected Enterprise: Huaihe Energy (Group) Co., Ltd.

The public notice period for this construction owner selection is 3 working days.

Entrusted by: Honghe Energy Bureau

Contact: Pan Chun

Phone: 0873-3900760

Agency: Honghe Construction Engineering Bidding Co., Ltd.

Contact: Hou Jianwei

Phone: 0873-3038448

March 20, 2026

Editor: Fengmang

View Original
This page may contain third-party content, which is provided for information purposes only (not representations/warranties) and should not be considered as an endorsement of its views by Gate, nor as financial or professional advice. See Disclaimer for details.
  • Reward
  • Comment
  • Repost
  • Share
Comment
Add a comment
Add a comment
No comments
  • Pin